Sinhagad Road metro: what is approved and when it may run

A metro line along Sinhagad Road is approved and contractor selection has begun. Where it stands in 2026, and why buyers should not pay for it yet.

Location5 min read
Pune Metro Line 4 from Khadakwasla along Sinhagad Road to Swargate and Kharadi, schematic

Sinhagad Road is due a metro line. Unlike a lot of infrastructure mentioned in property marketing, this one has been approved by both the state and the Union government. It is also, as of the latest reporting, a line with no construction contract, no published station locations and an unresolved junction at its city end. All of that matters if you are buying on this corridor.

What has been approved

The approvals came in stages, and each one is a real step.

WhenWhat happenedReported by
October 2024Maharashtra cabinet approves a Khadakwasla, Swargate, Hadapsar and Kharadi line of 25.518 km with 22 stations, at ₹8,131.81 crore, along with a 6.118 km Nal Stop, Warje and Manik Baug spurFree Press Journal, October 2024
November 2025Union Cabinet approves the two as Line 4 and Line 4A: 31.636 km and 28 elevated stations in all, at ₹9,857.85 crore, to be completed within five yearsPunekar News, November 2025
February 2026State grants revised administrative approval and authorises an agreement between the state, the Union government and Maha MetroFree Press Journal, February 2026
June 2026Maha Metro begins the process of appointing contractors for the Dandekar Bridge to Khadakwasla sectionPunekar News, June 2026

Punekar News reported in November 2025 that Line 4 serves Solapur Road, Magarpatta Road, Sinhagad Road, Karve Road and the Mumbai to Bengaluru highway, and meets the running Line 1 at Swargate. The Free Press Journal reported in February 2026 that the Union and state governments would each contribute ₹1,212 crore, with Maha Metro raising a loan of about ₹4,694 crore towards the rest.

The section that matters for Vadgaon

For Sinhagad Road, the relevant piece is the Dandekar Bridge to Khadakwasla section. Punekar News reported on 27 June 2026 that it is an elevated stretch of about 11 km with eight stations, that preliminary surveys of station locations and the viaduct alignment were under way before tenders were floated, and that construction is expected to take about three and a half years from the issue of a work order.

Punekar News also reported, in December 2025, that 105 pillars are planned between Rajaram Bridge and Vadgaon, running above the Sinhagad Road flyover, which will have to be partly cut at 66 points to make room. That side of the story is in the article on the flyover.

What we could not verify is a list of station names for this section. None of the official or news sources we checked publishes the eight station locations, and the June 2026 report says the surveys to fix them were still going on. Until Maha Metro publishes them, treat any claim of a station “near” a particular project as a guess.

What could slow it down

The most recent complication is at the city end. Construction World reported on 10 September 2026 that the PMC had decided on 4 September to build separate pillars for the metro and for the High Capacity Mass Transit Route at Dandekar Bridge chowk, a decision the publication said casts doubt on the Dandekar Bridge to Khadakwasla line. Maha Metro said it had received no formal communication from the PMC, and that it had already floated a tender and extended its schedule. Its director (works), Atul Gadgil, was quoted as saying final decisions could not be taken without a firm commitment from the PMC.

That is not a cancellation. It is the kind of disagreement between two agencies that can add months to a project, and it sits exactly where this line joins the rest of the network.

Other steps still ahead, from the same reporting:

  • Administrative clearances, which Punekar News said in June 2026 were expected over the coming months, before any contract is awarded.
  • The cuts to the Sinhagad Road flyover, which will disrupt traffic while the pillars go up.
  • The loan for the part of the cost the two governments are not paying.

A realistic timeline

The November 2025 approval speaks of five years. The June 2026 report speaks of about three and a half years of construction from a work order. As of the September 2026 reporting, no work order for this section had been announced.

Put those together and the arithmetic is simple. If a work order were issued at some point in 2027, three and a half years would take construction into 2030 or 2031, before testing, and before any slippage. That is our reading of the published figures, not a forecast from Maha Metro. Anyone who gives you a firm opening year for this stretch should be able to tell you where the year came from.

Why buyers should not price it in yet

A sanctioned metro line is a good reason to like a corridor over the long term. It is a weak reason to accept a higher price today, for four reasons.

  1. You pay now and benefit later. The seller is not carrying the risk of delay. You are.
  2. Station locations are not fixed. A station at the end of your lane and one a short drive away are different things, and nobody can yet tell you which you will get.
  3. Construction comes first. Years of pillar work over the flyover will make the drive worse before the trains make it better.
  4. Prices may already reflect it. Square Yards’ asking rate for Vadgaon Budruk rose from about ₹10,400 a sq ft in December 2025 to about ₹13,400 in March 2026, the quarter after the Union approval. Nobody can say how much of that is the metro, but it is a reason to be careful about paying for the same promise twice. The numbers are unpacked in the article on 2026 prices.

For Codename Vybe, the exact plot has not been published, so this site does not say how close it is to any future station. The location page covers the corridor as a whole. If you want the exact location so you can judge it against the alignment yourself, ask for it here.